Service Strategy

Flow

Process Control

Records & Reports

Time Needed (Days)

Customer RFQ

Receive (2D, 3D) Spec

Quotation

1 ~ 5 D

Pre-nomination

Internal Notice

Product Review

Part Review Meeting

DFM/Mold flow/PO

2 ~ 5 D, C. approval: 3 ~ 7 D

Mold Design (ECN)

3D Mold Design

Project Plan

7 ~ 21 D, C. approval: 7 ~ 14 D

Mold Manufacture

Tooling Meeting, Launch

Progress Report

25 ~ 55 D

Mold Test

Standard Mold Testing

Testing Parameter Report

1 ~ 2 D

Inspection

Mold / Parts Checking

Mold/Sample checking report

3 ~ 5 D

Mold Tuning

T1 Summary & Solution

Mold Tuning Data

7 ~ 14 D each trial

Customer Approval

Sample Approval

Mold Approval Form

2 ~ 5 D, C. approval: 3 ~ 7 D

Relocation / MP

Packing & Docu. Preparation

Shipping Document/PO

7 ~ 10 D

After Sales Service

Support & Maintenance

QC / Delivery

Summarization

Lesson Learned

Summary Report

×