Copyright © Shanghai MY Industrial Co., Ltd. All Rights Reserved. Site Map
Flow | Process Control | Records & Reports | Time Needed (Days) |
Customer RFQ | Receive (2D, 3D) Spec | Quotation | 1 ~ 5 D |
Pre-nomination | — | Internal Notice | — |
Product Review | Part Review Meeting | DFM/Mold flow/PO | 2 ~ 5 D, C. approval: 3 ~ 7 D |
Mold Design (ECN) | 3D Mold Design | Project Plan | 7 ~ 21 D, C. approval: 7 ~ 14 D |
Mold Manufacture | Tooling Meeting, Launch | Progress Report | 25 ~ 55 D |
Mold Test | Standard Mold Testing | Testing Parameter Report | 1 ~ 2 D |
Inspection | Mold / Parts Checking | Mold/Sample checking report | 3 ~ 5 D |
Mold Tuning | T1 Summary & Solution | Mold Tuning Data | 7 ~ 14 D each trial |
Customer Approval | Sample Approval | Mold Approval Form | 2 ~ 5 D, C. approval: 3 ~ 7 D |
Relocation / MP | Packing & Docu. Preparation | Shipping Document/PO | 7 ~ 10 D |
After Sales Service | Support & Maintenance | QC / Delivery | — |
Summarization | Lesson Learned | Summary Report | — |